COMMON QUESTIONS
Drawing: 1 month including time for quotation.
Sample: 2-4 months, depends molds opening needed or not.
Testing: 1 months for ridng testing and ISO EN testing.
Mass production: 3-4 monthsFrom the drawing to production deliver: 7-10 months
Material Purchase:
Tubes: 30-40 days
Foreign tubes: 40 days for production + 50 days via sea /10 days via air freight.
Hydro-formed tubes: 60 days for mold opening and first sample + 60-90 days for production
Forged parts: 60 days for mold opening and first sample + 60-90 days for production
CNC parts: 40 days
Frame production after all materials arrive:
Sample: 2 months (raw finished)
Mass production: 3-4months (raw finished)
Painting: 3~4 weeks
Decal mold: 1 month needed for mold opening"
Frame: 100PCS/size mixed.
Forged parts: 300-500PCS
investment casting parts: 300PCS
Hydroforming tube: 300PCS
Extrusion parts: 300KGS
Chromoly frame: 40,000PCS/per year.
Aluminum frame: 30,000PCS/per year.
The frame type will affect the capacity more or less.
Our main customers are from Europe and North American. Also we work with assemble factory and agents.
Our R&D team utilizes SolidWorks and AutoCAD to generate technical drawings.
3D frame drawing/3D 2D parts drawing like dropout, yoke , uncut tube and linkages ect... The specification of components like headset, BB and transmission system.
Caribou offer 2 years warranty and Product Liability Insurance.
30% of the total amount is due upon signing the Purchase Invoice (PI), and the remaining 70% is required before shipment. Price term for our transaction is FOB (Free on Board)